City signals end to stalled downtown hotel plan
The City of Woodstock says it will seek council approval to terminate a redevelopment agreement for a proposed downtown hotel after the developer was unable to close on required financing. The municipality announced the step on Friday, concluding a two‑year effort to bring a new hotel to the core near Calhoun Street and Jefferson Street.
Officials said the city had amended timelines and terms several times since the agreement’s approval in mid‑2024 in an effort to keep the project viable. Despite those extensions, the proponent, Kebb CS‑WK, LLC, could not meet funding conditions that were embedded in the deal.
“Not the outcome we hoped for,” city leadership said, adding, “Despite those efforts, the financing requirements outlined in the agreement could not be met.”
What council approved in 2024
Council voted in August 2024 to back a plan for a Cobblestone Hotels property downtown. The concept outlined a compact, service‑oriented hotel intended to support tourism, business travel and activity on the square. As approved, the development carried a total price tag of about $12.5 million, with up to $2 million in tax increment financing (TIF) support as a public incentive to help close the investment gap.
| Feature | Details |
|---|---|
| Rooms | 60 guest rooms |
| Amenities | Guest laundry, indoor pool, fitness centre, conference boardroom |
| Food & beverage | Breakfast room; outdoor patio slated to double as evening dining for Wissota Chophouse |
| Total project cost | $12.5 million |
| Public incentive | $2 million TIF |
How the process reached a breaking point
According to the city, staff and the developer had engaged for months on revisions to the original redevelopment agreement, aimed at giving the proponent more time and flexibility to meet lender requirements. Those amendments were not enough to bridge the financing shortfall. The city emphasized it appreciated the developer’s good‑faith efforts, but said the core funding conditions remained unmet and the file could not reasonably advance under the current terms.
The formal termination of the agreement is slated to come to city council for a vote on Tuesday. Until council acts, the agreement remains in place, but the administration’s recommendation is clear: end the pact and close this chapter of the file.
What this means for the downtown core
The decision removes one of the higher‑profile redevelopment proposals in the downtown pipeline. A hotel of this size, with on‑site amenities and dining, was pitched as a way to generate steady overnight stays and related spending in the core. Without the deal in place, the site near Calhoun and Jefferson remains open to future proposals, but no alternative has been put forward in the city’s statement.
- Location: Downtown Woodstock, near Calhoun St. and Jefferson St.
- Project status: Developer unable to secure financing; administration recommends terminating the agreement.
- Public funds: Up to $2 million in TIF had been approved within a $12.5‑million plan.
Next steps and accountability
Council’s upcoming vote will determine whether the agreement is formally dissolved. If approved, the city can seek new expressions of interest for the site or revisit development objectives for the immediate area. Officials did not outline a replacement timetable in the announcement.
For residents and businesses, the near‑term impact is that earlier expectations for a 60‑room hotel, associated hospitality jobs and added visitor traffic are now on hold. City staff underscored they had exhausted reasonable avenues to extend deadlines but could not waive fundamental financial conditions meant to protect public risk attached to the TIF incentive.